Date | Change | Source |
---|
24 Sep 2024 | Fr1 added, and 1872 frame noted as destroyed | Peter Hayward via #487 |
16 Sep 2024 | PN is Tuesday | Andrew Webster, local contact |
| Project complete; test ring took place 28/Jun/2024 | Andrew Webster, local contact |
21 Aug 2024 | 1,2: weight, nominal, note, date, founder, canons, turning, hanging added | Matthew Higby |
22 Dec 2023 | Project description amended | Jo Blyth, Office Manager, Blyth & Co Ltd. |
14 Dec 2023 | Project started. Bells now removed. | Tom Blyth, Blyth & Co |
13 Nov 2023 | Fr1: layout added | Video in Bellringers group 12/11/23 |
16 Sep 2023 | New project added | Jo Blyth, Office Manager, Blyth & Co Ltd |
29 Jun 2020 | fr1: material amended,date,maker,truss added | Tim Jackson via e-mail |
21 Jun 2020 | 1-8: frameid added | [James Hedgcock] via 00013856 |
| 1-8: nominal added; fr1: details added | Chris Pickford via 00013857 |
20 Jun 2020 | 1-8: turning,canon info added | Tim Jackson via e-mail |
12 May 2014 | Indication of toilet facility added | TimJ#199 via e-mail |