All changes to tower
Date | Change | Source |
---|---|---|
13 Apr 2023 | Fr1: material amended | Hugh Pettifer |
30 Mar 2023 | Postcode amended; overhaul descriptions amended; 3: diameter amended; 1-6: turning amended | Hugh Pettifer #004804 |
21 Aug 2022 | 1-6: weight, nominal, note added | Information (photo of Mears board in the tower) provided by Chris Winkless-Clark, from personal visit |
1908, 1934 overhauls, Fr1 added; 1-6: canons, turning added | Andrew Nicholson | |
15 Apr 2022 | Completion date amended | Andrew Nicholson |
13 Apr 2022 | Project completed | Andrew Nicholson |
8 May 2021 | Nicholson project under way. Heavy overhaul; stabilisation work to bell frame. | Andrew Nicholson |
3 Jun 2013 | Availability of toilet facility added | TimJ#190 via e-mail |